The Prairie Du Sac Dam has been sitting on the Wisconsin River and providing power to neighboring communities for the last century. Built in 1911, the dam was constructed using more than 12,000 timber piles in sandy soils. The original timber pile foundation successfully supported the dam for more than a century, but as historic wetting and drying of piles caused deterioration as the tail waters receded.

The dam's owner, Alliant Energy, proactively initiated a program to investigate the severity of the situation and to develop a plan to remediate the foundation system supporting the dam to maintain its integrity.

Nicholson is working as the General Contractor at the dam, installing an intricate micropile and anchor solution to support the dam. Let's drill down into our work at Prairie Du Sac Dam!

Want to know more?

If you have a similar project or questions, we can help. Get in touch with an expert today.

Dan Thome, P.E.
4124 Douglas Avenue
Kalamazoo, MI 49004
269-353-8421
Sign Me Up
Thank you! Your submission has been received. Keep your eyes out for our next Drill Down!
Oops! Something went wrong while submitting the form.

Never miss a Drill Down.

Sign up to receive our quarterly newsletter and drill down on some of our most interesting projects.

Join our team!

Work (and play) alongside some of the very best in the industry.